September 5th through Saturday, September 8th, crews will be preparing the stretch of McCarran Boulevard between South Virginia Street and Mira Loma Drive for paving work. Then that part of the project is set for the next week, September 12th through the 15th.
During that time, the road will be open in both directions except Saturday, the 15th when Rio Poco will be closed at McCarran in the morning and Mira Loma at McCarran will be closed in the afternoon.
This construction is all part of a $16 million project to improve and widen South McCarran Boulevard.
Written by Rebecca Cronon